Samuel Atta Akyea, Minister for Works and Housing

Minister of Works and Housing, Atta Akyea, has suggested the contractor that worked on the Saglemi Housing Project under the erstwhile John Mahama administration bewitched the then Ministry for Water Resources, Works and Housing (MWRWH) into paying huge sums of monies without evidence of work.

According to him, the Ministry paid a sum of US$80 million representing 40% of the contract sum as mobilization to the Contractor.

This racket, he said, was so strong that the Ministry did not demand a performance bond as a necessary prerequisite before releasing the money.

He said, “I do not know if the then MWRWH had been bewitched by the Contractor.”

“I submit that the seed of the bankruptcy of the Saglemi Housing Project was sown by this dubious act,” he stated.

Mr. Atta Akyea leveled the allegation when he responded to a Parliamentary question on the state of the Saglemi Housing Project posed by MP for Nsawam Adoagyiri, Frank Annor-Dompreh.

According to him, Parliament granted approval for the construction of 5,000 affordable housing units by Messrs Construtora OAS Ghana Limited with a buyer’s credit of US$200 million.

The project, he said, was subsequently downsized to 1,502 housing units, strangely with the same contract sum of US$200 million.

He said, “On 21st December, 2016, 14 days after President John Dramani Mahama had lost in the elections, the then Chief Director, Alhaji Ziblim Yakubu and the Contractor, reviewed the first amended and restated agreement and signed the Second and Restated Agreement, in which the scope of the works were reduced to 1,024 instead of the parliamentary-approved 5000 housing units, 388 to be finished completely externally and 90 units to be left at foundation or lintel levels.”

“This brings the total units to be constructed to 1,502 units at a revised contract sum of US$181,519,000.”

According to him, in July 2017 the new Chief Director reviewed the Second amended and restated agreement and signed a Third Amendment and restated EPC Agreement. This, he said, extended the period to December, 2017, to allow the contractors to complete the project.

“The scope in the Second and Restated Agreement was maintained but the contract price was reviewed further downwards to US$181,018,000.00,” he stated.

According to him, the Attorney-General has asserted that the contract has elapsed since May 2019 and suggested that all the agreements signed by the then Minister Collins Dauda and the Chief Directors after the original contract had received parliamentary approval are void and have no legal consequence.

He explained that the Ghana Institute of Surveyors has been engaged to conduct a value-for-money audit.

Their finding, he said, will indicate the extent of embezzlement of state resources via the affordable housing delivery.

“All the traducers of the law will be arraigned before a court of competent jurisdiction to answer criminal charges and civil action shall be used to recover monies lost to the state.”

“The audit will also project how much money would be required to complete the 5000 housing units with full amenities,” he said.

The Minister, however, pledged government’s commitment to complete the project in accordance with Article 35(7) of the constitution.